Reconstruction of the runway 12-30 at Nikola Tesla Airport 

Project carrier: 

Ministry of construction, transport and infrastructure

"Nikola Tesla" Airport, Belgrade

Project title: 

Reconstruction of the runway 12-30 at Nikola Tesla Airport

 

Investor: 

"Nikola Tesla" Airport, Belgrade

Designer: 

Public procurement procedure for selecting the best bidder for the development of technical documentation for the analysis of variant solutions for the improvement of the pavement structure of the runway is in progress. After this procedure, the conditions for starting a public procurement procedure for the development of technical documentation for the execution of works will be determined.

 

The significance of the project: 

Secure and safe air traffic, increasing the quality of the airport's basic resources.

Status of the project: 

The procedure for the production of technical documentation for analyzing variant solutions for improving the track construction of the runway is underway. The results of the analysis will determine the extent to which the work on the reconstruction of the runway 12-30 will take place.

 

Investment value: 

45 000 000 euros – reconstruction

Start of the project: 

2016

Completion of the project: 

2019

Source of finance: 

Private sector participation (PSP) or other sources of financing

Project description: 

The repair of rigid road construction PSS was last carried out in 2005 by scraping the asphalt wear layer and by setting a new one based on a project developed by the Institute for Roads. Due to the damage in the shape of reflected cracks that appeared in the wearing layer and due to the damage to the supporting structure, reconstruction should be performed, which depends on the results of the technical documentation-analysis that is in progress.

Level of physical realization: 

The process for preparation of technical documentation for the analysis of variant solutions for the improvement of the pavement structure of the runway is underway.

Level of financial realization: 

No payments were made at this stage of the project.